Lydstep Terrace, Bristol

Steel Framing: Lydstep Terrace

Steel Framing: Lydstep Terrace

Hadley Steel Framing knew where to turn when they needed help with a tricky development of nine townhouses, close to the River Avon in Bristol. After nine years of​ ​collaborating on projects with key members of the CGS team, they already knew they could count on us to deliver.

Facts & Figures

Project Location

Lydstep Terrace, Bristol

End Client

RBH Properties

Main Contractor

Hadley Steel Framing

Project Cost

£135K

Time On Site

12 weeks

The Challange

Keeping local residents fully informed during the Lydstep Terrace development was vital, given the site lies within a highly-populated area, close to homes, with restrictive access to the site. Carrying out the work in the middle of the COVID-19 pandemic was a huge challenge for everyone involved, but we followed very strict protocols to keep residents happy and workers save.

The Solution

CGS supplied teams of no more than eight installers at any time, ensuring social distancing regulations were met, meaning any worries local people might have had were allayed and the project was completed on time and on budget in just 12 weeks. “We have an excellent working relationship with Hadley because myself, and the site managers have direct links into their business. This means we can ensure the design teams, the panel production, the transport and commercial teams all work seamlessly together,” said CGS Director Chris Martin.

double quote

“Time is money in business, and right now every penny counts. I have complete confidence that the team from CGS will deliver and that’s worth its weight in gold.”

Steve Chesters, Commercial Manager at Hadley Steel Framing

Project Gallery

No items found.

Costs to a Minimum

“The other great benefit for Hadley is our project management and installation costs are a one-off cost and not a fixed cost to their business, so once construction is completed so is the cost to them,” said Chris.
The project was a big success for the developers RBH Properties, CGS, Hadley and their contractors Swinhay. The model worked really well and will be used again.

Lessons for the Future

“At CGS we’re always looking for ways to give our clients better value for money and to work collaboratively with our partners.
“During this build, we learned even more about Hadley’s processes, around quality control, site handover and design. This means we will be one step ahead next time and able to work even more efficiently in the future,” said Chris.

Hadley Steel Framing feature in LSF Magazine

Hadley Steel Framing was featured in the May 2020 issue of Light Steel Framing Magazine.

For more information: hadleygroup.com or rbhproperties.co.uk